BMS Replacement and Configuration (Integrated)
 

Power Pack Replacement (Modular) Power Pack Replacement (Ingetrated)

The BMS is located inside the power pack, behind the top power pack cover.

Required Tools

• Computer with Tera Term installed

• 3mm Hex wrench

• 40-04778 REV03 13MY PROG AND DIAG ASSY

• 56-06442 REV03 DONGLE MY14 BMS PROG TO MY13 PROG AND DIAG ASSY

Removal Procedure

Important: REMOVE the B+ fuse before removing the BMS board.

The low power B+ Fuse is located on the power pack, below the data link connector.

To access the low power fuse (left side):

1. Ensure that the key switch is in the OFF position.

2. Remove bolt (1) securing the fuse cover.

3. Remove cover (2) to gain access to the fuse.

4. Unscrew the fuse cap (3) and withdraw the fuse from the power pack.

22083

5. Remove the power pack. Refer to Power Pack Replacement (Ingetrated).

Note: Clean/remove and dirt or water from the front of the power pack cover prior to removal.

6. Remove the 9 screws (1) from the front of the power pack, and carefully remove the front cover (2). There may be some resistance caused by the cover sealant.

7. Disconnect the connector (2) on the upper edge of the board by pressing in retaining tab (A) then pushing up (B) on the connector.

8. Remove the screw (1) with an external tooth washer.

9. Remove the 2 cell-tap nuts (5) from the BMS.

10. Remove the socket head screws (4) holding the board to the battery.

11. Gently pull out on the cell-tap connector (3) on the upper edge of the BMS, while supporting the BMS board.

12. Ensure that the cell-tap connector upper gasket (D) and lower gasket (C) are in place and not stuck to the old BMS board

Installation Procedure

Important: DO NOT reinstall the B+ fuse until the BMS is fully connected and mounted.

1. Ensure that the lower gasket (C) and upper gasket (D) are in place.

2. Press down on white cell-tap connector (3) while supporting the rest of the board to ensure the BMS goes in straight.

3. Press down on connector (2) on left side of BMS while supporting the other side. An audible click will be heard when the connector is fully engaged.

4. Replace the socket head screws (4) holding the BMS in place.

5. Replace the screw (1) with the external tooth washer in the location shown.

6. Replace the 2 cell-tap nuts (5) and tighten.

7. Plug-in to BMS programming connector with a computer with Teraterm installed (see service bulletin SV-ZMC-14-202 Log Pulling with Tera Term for Tera Term setup instructions).

8. Once connected to the BMS login with the command ‘login wideopenthrottle’ and you should see the message ‘Logged in at level 2’.

9. Set the date and time with the command ‘set time MM DD YYYY HH MIN SEC’ using that format to enter date and time. The time is measured using a 24 hour clock

10. Set the size of the battery by entering the command ‘set numbricks X’ where X is either 3, for a ZF9.8 system, or 4 for a ZF13.0 system.

BMS-Config_1

11. Once the date/time and size of the battery have been set, disconnect the computer from the BMS.

12. To ensure the board you just installed has the latest firmware, connect to the OBD-II connector and use the firmware update tools outlined in bulletin SV-ZMC-14-077.

13. Cover programming connector and push buttons with compound 70.

14. Install the power pack front cover (2) and install the 9 screws (1).

15. Install the power pack. Refer to Power Pack Replacement (Ingetrated).

16. Install fuse and cap.

17. Install cover (2) and tighten bolt (1) to 1.3 N•m (10 lb in).